View Single Post
Unread 10-11-2004, 01:46 AM   #37
Becks
Cooling Neophyte
 
Join Date: Mar 2004
Location: Cali
Posts: 13
Default

"8/27- The CSP 750 Pumps are on pre-order again. These are going to be the new Mark II versions. I will get pictures posted when I can get ahold of some. Epected time of delivery is in 2 weeks so get your order in now as they will sell out fast."

8/27 + 2 weeks = ...

9/27 "The pumps are shipping this week to us. It should be about 5 days until they arrive to us."

9/27 + 5 days = ...

"10/05- The CSP Mark II pumps are assembled and ready to ship to us in a day or two. From there it takes anywhere from 3-5 days to arrive depending on customs."

10/10 + 7 days = ...

Most likely it'll be 2 months of waiting on these pumps.. without ONCE saying "_____ reason the pumps are being delayed"

"I wanted to get an actual timeframe before posting anything on this site as far as status goes since it was changing day by day. There will be more information when they arrive."
... that makes no sense, maybe you would get an actual timeframe before setting a new date, but you would not wait on a actual timeframe to inform that the current date is no longer has any meaning.


Low prices or convenience is not going to make me order from dtek again, I'll go out of my way from now for the principle of it. Honestly I have no reasons to have the pumps now anyways, had I gotten them a month ago they would have been on my shelf... the only thing that pisses me off is the way dtek has handled this (and previous preorders). The funny part is, I've always found people to be VERY understanding when you just keep them informed... heh, I don't know why this is bothering me so much.
Becks is offline   Reply With Quote